'Delays won't be tolerated': Maharashtra CM Devendra Fadnavis sets 2027 deadline for Mumbai's Ambedkar memorial, warns contractor of replacement

Newspoint
MUMBAI: With the Ambedkar memorial at Indu Mill falling behind schedule, chief minister Devendra Fadnavis has warned the contractor that delays will no longer be tolerated, directing that the long-pending project be completed by 2027.

Taking a tough stand, Fadnavis has also asked officials to explore replacing the contractor if it lacks the capacity and commitment to complete the work, making it clear that financial disputes cannot be allowed to hold the project hostage.

Fadnavis directed the Mumbai Metropolitan Region Development Authority ( MMRDA ) to monitor the project’s progress daily and asked the contractor to submit a revised work schedule to the high-powered committee, specifying clear timelines for completion.

At a review meeting held at Sahyadri Guest House , the chief minister took stock of the project’s progress, including structural steel fabrication and installation, bronze cladding , construction quality and the contractor’s additional financial claims .

Fadnavis said completing the work in accordance with the contractual terms and conditions was the contractor’s responsibility.

He directed officials to assess the agency’s capacity and commitment and consider appointing an alternative contractor, besides other stringent measures, if required.

On the contractor’s financial claims, the chief minister asked officials to examine the contractual provisions, changes in GST rates, escalation indices and costs arising from additional work.

A legal opinion should be obtained on the applicability of GST-related provisions in the contract, he said. The proposal to release an advance payment against a bank guarantee to facilitate the purchase of material required for bronze cladding should also be examined.

The chief minister directed that structural steel installation and bronze cladding be carried out simultaneously through better coordination.

The revised schedule should clearly specify the availability of materials, machinery, manpower, fabrication requirements and construction milestones, with responsibilities and deadlines assigned for each stage. He also stressed that there should be no compromise on the structural quality , safety and stability of the memorial.

Social justice minister Sanjay Shirsat said the memorial was an important project closely connected with public sentiment and should not be treated as just another infrastructure project.

He said the contractor could not justify keeping work suspended for 10 months on any pretext and must take responsibility for completing it within the stipulated period. The government would examine legitimate financial claims as per rules, but these should not hold up construction.

Deputy CM Sunetra Ajit Pawar, minister Ashish Shelar, minister of state Madhuri Misal, BMC commissioner Ashwini Bhide, MMRDA metropolitan commissioner Sanjay Mukherjee and senior officials of the state government, contractor Shapoorji Pallonji and project consultants attended the meeting.